ADR View

Ampacity quantification and modeling tool, based on historical weather data

LEARN MORE

ADR Sense

Self-powered vibration sensor with GSM data transmission

LEARN MORE

ADR Operate

Ampacimon’s data-acquisition and ampacity computation real-time engine

LEARN MORE

ADR Trend

1-4 hours ampacity forecast software

LEARN MORE

ADR Horizon

60 hours ampacity forecast software using weather forecast data

LEARN MORE

MAINTENANCE OPTIMIZATION 2017-02-03T09:35:20+00:00

CASE STUDY #2

Optimising existing lines during scheduled maintenance

Facts :

A critical 220 kV line must be consigned for several months for scheduled maintenance.

Constraints :

Disconnecting this line entails large costs due to re-despatch plans.

Ampacimon solution :

An adjacent line was equipped with 4 ADR Sense modules and monitored with ADR Operate real-time analysis software. For 3 months, this adjacent line could take in the additional load, namely an average 40% extra capacity.

Ampacimon solution make possible for grid operators to set up maintenance plans that are much more flexible, less constraining, less costly, and quickly underway.

RELATED PRODUCTS

ADR View
ADR Sense
ADR Operate
ADR Trend
ADR Horizon

TÉMOIGNAGE CLIENT

« Les informations fournies par les modules d’Ampacimon sont constamment prises en compte par nos opérateurs, en temps normal mais surtout en situation tendue. Les limites réelles et instantanées de notre réseau sont ainsi connues.  Grâce à un investissement relativement limité, Elia peut donc, au bénéfice de tous, régulièrement repousser l’activation de parades coûteuses. »

Monsieur Raphaël Bourgeois

BACK TO CASE STUDIES
Latest news

You couldn’t attend the webinar on July 29th? The registered version is now available…

August 6th, 2019|0 Comments

Find the webinar recorded version here. This webinar introduces the physics of Dynamic Line Rating [...]

Webinar on 29th July : Join us to find out about the current developments of dynamic line rating (DLR).

July 10th, 2019|0 Comments

Learn about: - How DLR data have been integrated into grid operators' processes, - How cross-border [...]

Don’t miss next CIRED – June 2019 in Madrid, Spain

May 16th, 2019|0 Comments

3-6 June 2019 : the leading Forum for Electricity Distribution experts Meet with up with 2000 intern [...]